Designers Hate Estimating, Pt. 2 of 3
June 24, 2008
In Pt. 1 of this series, I introduced Construx's "cone of uncertainty" and how to narrow the risk in your estimates by determining what unknown variables exist in your project scope.
Let's work through what these variables usually are, and how they can be brought in line in your estimate.
Define the Problem before You Estimate
In your estimate, what you need to demonstrate most is your understanding of the problem. Your approach to how it should be solved would follow, and should always be consistent. As a quick example, let's think through the variables that exist in creating a new logo for a local business.
Many years ago, I would estimate doing a logo by looking back through previous project to see how long it took for a project of a similar type, bash together an estimate based on how long they think it would take, multiply it by 1.3x to give some cushion for contingency, slot in some money for printing costs if they need to create any supporting materials as part of their bid, and send it off to the client.
Today, I focus more closely on what the client needs before I think about how I'm going to create it -- even if I've done a similar type of project for them before. And I charge my client for this extra time spent on the estimate as part of my overhead and creative fee, because they're getting more than just a cost for creating a logo.
Let me try to break it down here.
There's data from your prospective or current client, relating to specific needs out of the project (looking for brand lift, increase in perception, greater sales, etc.), as well as competitive analysis and market research.
There's qualitative information that your client provides in the way of what customers and staffers think about the old logo, which adds up to an impression of why they need a new one. These elements shape up into a business problem, which must then meet your process.
This information can usually be teased out in a single phone call, with some follow-up via email. I recommend making a set of questions you always ask in the exploratory call and keeping them by your phone in case you're surprised by an opportunity.
Have a Consistent Process for Creating the Solution
Within that same exploratory phone call, you should delineate what standard steps the client would take through the project, and what they are given with regard to rounds of review per each deliverable as part of the scope of work. Get that on the table from your very first conversation, so they're aware that they will follow your working process, not vice-versa.
It should go without saying that all of your rounds of review and costs for work outside the scope of the proposal must be in writing to protect your interests. I also recommend providing an hourly estimate of your work for a project, not a flat fee. There is always risk in accepting a flat fee, as it places the onus on you for understanding all the ways a project could go sideways and accounting for them.
There's qualitative information that you control in forming your estimate, such as what kind of creative approach you think you'd take -- but I'd recommend articulating that in your creative brief. I wouldn't recommend writing the brief before getting a signature and a portion of your fee, but I generally have a glimmer of an idea of what approach I'd likely take. This thinking can sometimes provide some color in the estimate, but should never be doled out for free and can sometime be shared anecdotally if the client is looking for a detail to tip the scale in their choice of a designer.
In Part 3 of this series, we'll explore some of the incidental details that many designers overlook when estimating a new project.